miroir/notes
jedarden 24b4102d33 Phase 5: Update verification document - all 21 capabilities complete
Updated the Phase 5 verification document to reflect that the canary
runner (§13.18) is now fully implemented with:
- All assertion types (top_hit_id, top_k_contains, min_hits, max_p95_ms,
  settings_version_at_least, must_not_contain_id)
- Background runner with per-canary scheduling
- Run history tracking (canary_runs table)
- Metrics emission
- Capture-from-traffic flow

All 21 §13 Advanced Capabilities are now complete.

Co-Authored-By: Claude Opus 4.7 <noreply@anthropic.com>
2026-05-03 20:42:41 -04:00
..
miroir-mkk.md P4: Phase 4 topology operations verification — all chaos tests pass 2026-05-01 10:52:49 -04:00
miroir-r3j-final-retrospective.md P3: Add Phase 3 final retrospective and verification 2026-05-02 18:25:42 -04:00
miroir-r3j-final-verification.md P3: Add final verification note for Phase 3 completion 2026-05-03 15:14:22 -04:00
miroir-r3j-phase3-completion-summary.md P3: Complete Phase 3 — Task Registry + Persistence (SQLite + Redis) 2026-05-02 17:14:29 -04:00
miroir-r3j-phase3-completion.md Phase 3: Verify Task Registry + Persistence completion 2026-05-03 15:33:34 -04:00
miroir-r3j-phase3.md P3: Add Phase 3 retrospective and verification notes 2026-05-03 08:30:38 -04:00
miroir-r3j-verification-session.md P3: Add verification session notes for bead closure 2026-05-02 18:04:34 -04:00
miroir-r3j-verification-summary.md P3: Verify Phase 3 Task Registry + Persistence completion 2026-05-02 17:15:58 -04:00
miroir-r3j-verification.md P3: Add Phase 3 verification summary and close bead 2026-05-03 08:30:38 -04:00
miroir-r3j.md P3: Add Phase 3 completion verification summary 2026-05-03 08:36:30 -04:00
miroir-uhj-phase5-verification.md Phase 5: Update verification document - all 21 capabilities complete 2026-05-03 20:42:41 -04:00